The Transportation Division encompasses all aspects of transportation, including maintaining and repairing existing
streets, roads, and sidewalks, the planning and financing of existing roads and future proposed roads. This division
will also interact with Federal, State, and County agencies to meet the current and future transit, mobility, and
transportation needs of the community. The department works with other utilities to insure a collective effort for all
utility maintenance prior to beginning roadway maintenance or new construction. Rehabilitation and maintenance of
roadways are funded by both an approximate $1.25 million annual general fund transfer and an approximate $3.2
million annual 1/4 cent sales tax collected and assigned to street maintenance. The department assists in
coordinating transportation projects and related issues, as well as, to provide support to both the Georgetown
Transportation Enhancement Corporation (GTEC) and the Georgetown Transportation Advisory Board (GTAB).
This Division is funded in the General Fund and the Stormwater Drainage and Street Tax Special Revenue Funds.
Transportation
Stormwater Drainage
Page 162
Administration
Page 160
Street Department
Page 164
07/08 07/08 08/09 PROPOSED BUDGET
AMENDED PROJECTED NEW % CHANGE
BUDGET ACTUAL BASE PROGRAMS TOTAL (PROJ. ACTUAL)
General Fund
Administration 314,335 172,042 325,926 170,000 495,926 188.3%
Streets 2,922,605 2,807,132 2,884,308 150,000 3,034,308 8.1%
total General Fund 3,236,940 2,979,174 3,210,234 320,000 3,530,234 18.5%
Other Enterprise Funds
Stormwater Drainage 988,388 *1,035,180 1,167,540 175,000 1,342,540 29.7%
total Other Ent. Funds 988,388 1,035,180 1,167,540 175,000 1,342,540 29.7%
Division Total 4,225,328 4,014,354 4,377,774 495,000 4,872,774 21.4%
*Year end budget amendment will be taken to City Council.
PERSONNEL
SUMMARY
PERSONNEL OPERATING CAPITAL TOTAL (FTE's)
General Fund
Administration 308,496 187,430 495,926 3
Streets 970,691 778,617 1,285,000 3,034,308 18.75
total General Fund 1,279,187 966,047 1,285,000 3,530,234 21.75
Other Enterprise Funds
Stormwater Drainage 277,007 1,065,533 1,342,540 5.5
total Other Ent. Funds 277,007 1,065,533 1,342,540 5.5
Division Total 1,556,194 2,031,580 1,285,000 4,872,774 27.25
Uses & Expenses
Transportation
08/09 PROPOSED BUDGET
Transportation
Administration
DEPARTMENT DESCRIPTION
The Transportation Division encompasses all aspects of
transportation, including maintaining and repairing existing
streets, roads, and sidewalks, the planning and financing of
existing roads and future proposed roads, as well as,
stormwater management. This division also interacts with
Federal, State, and County agencies to meet the current and
future transit, mobility, and transportation needs of the
community. The Administration department works with other
utilities to insure a collective effort for all utility maintenance
prior to beginning roadway maintenance or new construction.
Rehabilitation and maintenance of roadways are funded by
both an approximate $1.25 million annual general fund
transfer and an approximate $3.5 million annual 1/4 cent sales
tax collected and assigned to street maintenance. The department assists in coordinating transportation projects
and related issues, as well as, to provide support to both the Georgetown Transportation Enhancement Corporation
(GTEC) and the Georgetown Transportation Advisory Board (GTAB).
MAJOR DEPARTMENT GOALS
Provide efficient and effective Transportation systems that serve the community and reflect its values.
Explore financing options for Capital Improvement Projects (CIP) and Transportation expenditures that
presently do not have a funding source.
Identify and implement economical maintenance techniques for city roadway maintenance.
MAJOR DEPARTMENT ACCOMPLISHMENTS FOR FISCAL YEAR 2007/2008
Hired Director to oversee new transportation projects, boards, and work with other governmental agencies, as
well as, to provide oversight to the City’s transportation and stormwater drainage systems within the division,
and determine organizational structure.
MAJOR DEPARTMENT STRATEGIES FOR FISCAL YEAR 2008/2009
Update 10-year Transportation Plan process for GTEC.
Develop and implement a traffic management plan to include signals, signs, speed limits and other traffic
calming measures. (Policy Principal 3.0 A / Priority Area B)
Assume responsibility for signalization of traffic lights within the city.
Incorporate transportation organizational functions to enhance mobility within the city.
Evaluate costs for Traffic Signal Control and needed upgrades.
Develop plan to assume responsibility for signalization of traffic lights within the city, with expected
implementation before 2010.
160
ADMINISTRATION
06/07
ACTUAL
07/08
ORIGINAL
BUDGET
07/08
FINAL /
ACTUAL
08/09
ADOPTED
09/10
PROPOSED
Transportation Director 0 1 1 1 1
Transportation Engineer 0 1 1 0 0
Project Manager 0 1 1 1 1
Principal Planner 0 0 0 1 1
TOTAL 0 3 3 3 3
WORKLOAD MEASURES
ACTUAL
FY 05/06
ACTUAL
FY 06/07
BUDGETED
FY 07/08
PROJECTED
FY 07/08
PROJECTED
FY 08/09
1. Number of traffic signals N/A N/A 3 3 1
2. Number of lane-miles 425 490 529 529 540
3. Number of Transportation CIP
projects
N/A
N/A
8
8
6
PERFORMANCE MEASURES
ACTUAL
FY 05/06
ACTUAL
FY 06/07
BUDGETED
FY 07/08
PROJECTED
FY 07/08
PROJECTED
FY 08/09
1. % of projects completed within
budget
N/A
N/A
100%
100%
100%
2. % of projects completed on
schedule
N/A
N/A
100%
100%
100%
3. % of customers reporting
noticeable traffic improvement
N/A
N/A
60%
60%
60%
DEPARTMENTAL BUDGET: GENERAL FUND
07/08 09/10 06/07 07/08 PROJECTED 08/09 ESTIMATED
ACTUAL BUDGET ACTUAL ADOPTED BASE
308,496306,405 164,112 Personnel 309,100
7,930 7,930 Operations 17,430187,430
495,9260314,335 172,042 326,530
007/08 was the first year for this department. Previously, this function was included in Georgetown Utility Systems
MAJOR BUDGET CHANGES/ISSUES:
2
(GUS). Various positions were reassigned, as the focus and objectives of this division were refined.
161
Transportation
Stormwater Drainage
DEPARTMENT DESCRIPTION
The Stormwater Drainage Utility addresses environmental
concerns over in-stream water quality, regulatory demands
related to stormwater run-off controls, infrastructure operation
and maintenance, and drainage/flood control related capital
project needs. Other duties include sign maintenance for the
Street Department and assisting Police and Fire Services on
Code Enforcement issues.
MAJOR DEPARTMENT GOALS
Comply with Stormwater regulations.
Reduce the threat of property damage and personal injury, and enhance public safety through proper
maintenance and operation of the city’s drainage system.
Improve the cleanliness and appearance of the community through the sweeping of city streets.
MAJOR DEPARTMENT ACCOMPLISHMENTS FOR FISCAL YEAR 2007/2008
Constructed drainage structures along Railway to help alleviate flooding between 21st at Church, Pine and 10th
Completed construction of two large water quality ponds serving the downtown area.
Contracted with consultant to determine the needs of the eroding banks of historic retaining wall in San Gabriel
Park.
MAJOR DEPARTMENT STRATEGIES FOR FISCAL YEAR 2008/2009
Develop and implement a on-going stormwater maintenance program that meets impending federal
regulations. (Pollution Prevention Plan) (Policy Principal 4.0 D / Priority Area L)
Contract engineering services to design the Maple Street culvert improvements and receive environmental
clearance.
Design and install protective erosion control on the north bank of the San Gabriel River to prevent further
damage to the river banks and park land.
Replace Oak Tree Drive low water bridge in Berry Creek to insure proper drainage and improve safety.
Utilize the Regional Stormwater Master Plan (RSMP) by building detention ponds and upgrading waterways as
needed within the city. (Policy Principal 4.0 G / Priority Area )
162
STORMWATER DRAINAGE
06/07
ACTUAL
07/08
ORIGINAL
BUDGET
07/08
FINAL /
ACTUAL
08/09
ADOPTED
09/10
PROPOSED
Drainage Foreman 0 1 1 1 1
Light Equipment Operator 0 1 1 1 1
Heavy Equipment Operator 0 1 1 1 1
Street Sweeper Operator 0 1 1 1 1
Sign & Field Technician 0 1 1 1 1
Crewman I (P/T) 0 0.5 0.5 0.5 0.5
TOTAL (FT/PT) 0 5/.5 5/.5 5/.5 5/.5
WORKLOAD MEASURES
ACTUAL
FY 05/06
ACTUAL
FY 06/07
BUDGETED
FY 07/08
PROJECTED
FY 07/08
PROJECTED
FY 08/09
1. Miles of public right-of-way mowed
and cleaned
25
36
36
36
36
2. Hours of street sweeper operation 1,500 1,600 1,600 1,600 1,600
3. Linear feet of curb and gutter
installed/replaced city wide
19,672
16,575
10,800
10,000
10,000
PERFORMANCE MEASURES
ACTUAL
FY 05/06
ACTUAL
FY 06/07
BUDGETED
FY 07/08
PROJECTED
FY 07/08
PROJECTED
FY 07/08
1. # of times city streets swept
annually
7
8
8
8
8
2. Cubic yards of debris prevented
from entering waterways
1,250
1,600
1,600
1,600
1,600
3. # of detention ponds maintained 23 34 34 38 38
DEPARTMENTAL BUDGET: STORMWATER DRAINAGE FUND
07/08 09/10 06/07 07/08 PROJECTED 08/09 ESTIMATED ACTUAL BUDGET ACTUAL ADOPTED BASE
277,007251,792 268,223 263,150 Personnel 278,799 1,065,533687,373 701,165 753,030 Operations 892,460 41,223 19,000 19,000 Capital
1,342,540 1,171,259980,388 988,388 1,035,180
163
Transportation
Street Department
DEPARTMENT DESCRIPTION
The Street department manages, maintains and repairs City
streets and rights-of-way. Responsibilities include traffic
control, emergency response operations, special events, and
assistance in code enforcement. Daily, the department
inspects roadways for sign repair, pavement management,
and sight obstructions. The Street department participates
with the Safety Committee to provide safety-training
workshops. The department also oversees the management of
revenues collected through the City’s ¼ cent sales tax for
street maintenance.
MAJOR DEPARTMENT GOALS
Continue work with Federal, State and County entities, adjoining municipalities, other departments and the
public to update and maintain a Comprehensive Transportation Plan with special attention to:
Development of a plan to connect Northwest Boulevard to Austin Avenue.
Development of programs to adequately handle traffic operations.
Protect the investment in the public transportation system through preventive maintenance and on-going
rehabilitation of streets and sidewalks.
MAJOR DEPARTMENT ACCOMPLISHMENTS FOR FISCAL YEAR 2007/2008
Rehabilitated the following proposed roadways using the ¼ cent street maintenance sales tax and General
Fund:
15th Street (Hart to Scenic)
Leander Street (22nd to 17th)
Northwest Blvd. (Northwood to Hedgewood)
San Gabriel Heights Subdivision
Sierra Vista Subdivision
Berry Creek (Section One ( Airport Rd. to Oak Tree)
Assumed maintenance responsibility for Austin Avenue from the Texas Department of Transportation (TxDOT).
Expanded signal control from 1 to 7 signals.
MAJOR DEPARTMENT STRATEGIES FOR FISCAL YEAR 2008/2009
Work with the Georgetown Transportation Advisory Board (GTAB) to possibly begin possible implementation of
Bond election road improvement projects if approved by voters in November.
Continue implementation of maintenance programming identified by the recently implemented pavement
management system to include:
15th Street (Church to Hutto)
Del Webb Blvd.
Pleasant Valley, Quail Valley, and Reata Trails Subdivisions
Railroad Avenue (2243 to SH 29)
Scenic Drive 2243 to 2nd Street
Old Town (between Church Street and College Street; and between 2nd and 8th Streets)
Continue work with Federal, State and County entities, adjoining municipalities, other departments and the
public to update and maintain a Comprehensive Transportation Plan with special attention to:
Development of a plan to connect Northwest Boulevard to Austin Avenue.
Development of a plan for the intersection at Del Webb Boulevard and Williams Drive.
164
Update 5 Year Capital Improvement Projects (CIP) using recommendations from the second evaluation of over
all pavement conditions.
STREET DEPARTMENT
06/07
ACTUAL
07/08
ORIGINAL
BUDGET
07/08
FINAL /
ACTUAL
08/09
ADOPTED
09/10
PROPOSED
Transportation Services Manager 1 1 1 1 1
Streets Superintendent 1 1 1 1 1
Streets Foreman 1 1 1 1 1
Crew Foreman 0 0 0 1 1
Light Equipment Operator 8 8 8 10 10
Heavy Equipment Operator 4 4 4 4 4
Street Maintenance Worker (P/T) .75 0.75 0.75 0.75 0.75
TOTAL (FT/PT) 15/.75 15/.75 15/.75 18/.75 18/.75
WORKLOAD MEASURES
ACTUAL
FY 05/06
ACTUAL
FY 06/07
BUDGETED
FY 07/08
PROJECTED
FY 07/08
PROJECTED
FY 08/09
1. Lane miles of seal coated,
overlayed or microsurfaced streets
33.5
7
10
7
10
2. Square feet of roadway patching 30,000 32,000 35,000 35,000 35,000
3. Traffic signs repaired/installed 350 500 600 1,200 1,200
4. Lane miles of streets maintained 385 425 490 529 540
5. Linear feet of sidewalk installed 300 500 3,000 2,800 2,800
PERFORMANCE MEASURES
ACTUAL
FY 05/06
ACTUAL
FY 06/07
BUDGETED
FY 07/08
PROJECTED
FY 07/08
PROJECTED
FY 08/09
1. % of streets seal coated 1.5% 1.0% 2.0% 1.5% 1.5%
2. % of streets overlayed 2% 2% 4% 2% 8%
3. PCI** adopted for GASB 34 85% 85% 90% 90% 90%
** PCI = Pavement Condition Index
DEPARTMENTAL BUDGET: GENERAL FUND
07/08 09/10
06/07 07/08 PROJECTED 08/09 ESTIMATED ACTUAL BUDGET ACTUAL ADOPTED
BASE
970,691697,781 820,830 794,892 Personnel 973,192 682,491 851,775 647,240 Operations 795,517928,617
675,473 1,250,000 1,365,000 Capital 1,100,0001,135,000
3,034,3082,055,745 2,922,605 2,807,132 2,868,709
165