HomeMy WebLinkAboutUtility CIP FY 2014/2015 C ITY OF G EORGETOWN , TEXAS C APITAL I MPROVEMENT P LAN U TILITY S ERVICES F ISCAL Y EAR 2014-15 Georgetown Utility Systems Advisory Board April 11, 2014 DR A F T Table of Contents Introduction ............................................................................................................. 01 Utility Operations Water Services Introduction………………………........................................................ 02 Water Projects ................................................................................... 06 Wastewater Projects .......................................................................... 09 Energy Services Introduction………………………………………………………..………14 Electric Projects…………………….………………………………..……16 DR A F T Capital Improvement Plan The City of Georgetown annually updates and adopts a five-year Capital Improvements Plan (CIP) Schedule as part of the operating budget adoption process. Needed capital improvements are identified through system models, repair and maintenance records, and growth. The City uses a team approach to prioritizing capital improvement projects, whereby City staff from all operational areas provide input and ideas relating to each project and its effect on operations, such as: Fire and Police Services staff provides insight into a project’s impact on emergency traffic responses, public lighting issues and other public safety concerns. Planning & Development staff gives direction regarding new development and the infrastructure needs relating to this growth. Other utility departments, such as the Transportation, Energy and Water Services Departments exchange information regarding each project and coordinated timing of many of the related projects in an effort to create less inconvenience for the citizens affected. The timeline for the CIP planning process is outlined below: By using this team approach, the City develops cooperation among the departments, identifies potential problem areas, and prioritizes financing issues. The Capital Improvements Projects (CIP) generally consists of infrastructure and related construction and do not include small capital items such as furniture, equipment and vehicles. Significant maintenance projects, such as street repairs are not included in the capital project schedules. These maintenance type projects are not capitalized as a fixed asset and are always cash funded; therefore, they are considered operational in nature and are included in the departmental operating budget. The CIP schedules consolidate the capital spending priorities for all operating activities of the City, including all governmental and enterprise activities that provide services to the citizens of Georgetown. The CIP Schedules are included as part of the annual operating budget. The first year of the list becomes the capital budget for the approved budget year. The following pages outline the CIP Schedule for each activity and include anticipated projects, current year project location and sources of funding. January Initial Department Meetings formulating projects in CIP February / March Division Meetings to coordinate projects in CIP Finalized funding plan May / June Present CIP to Boards and City Council September Adopted along with Annual Operating Plan Funding Operating Revenue 15,314$ Utility Revenue Debt 2,477 Impact Fees 1,270 Interest & Other 635 Total Funding 19,696$ Project Costs Georgetown Utility Systems Water Services 12,719$ Energy Services 6,903 Debt Issuance Cost 74 Total Project Cost 19,696$ 2014 / 15 Capital Improvement Summary (in thousands) 1 DR A F T Water Services Introduction Georgetown Utility Systems Water Services Utility maintains a Capital Improvement Program (CIP) to address the community’s need for superior water, wastewater, and irrigation service. This CIP is determined by many factors including on-going annexation, service improvement, the rehabilitation of aging water and wastewater infrastructure, and the need to meet changing state and federal requirements. The City operates three water treatment plants and five wastewater treatment plants. This table lists each plant with its current capacity. Water Services retains ownership of these plants and contracts for their operation. The City’s current utilization of its water supply is 40% ground water and 60% surface water. Growth Population growth within the Water Utility service area continues to drive the need for capital improvement. The City of Georgetown’s water and wastewater demand is projected to grow by approximately 15% over the next five years. The five year plan includes plans to expand the capacity of the water treatment system to meet peak demand. Wastewater flows are also anticipated to grow by approximately 18% over the next five years. City staff continues to look for ways to improve services within the current infrastructure, and thus delay plant expansions if at all possible. Water Treatment PlantsMGD Lake Water Plant 19.800 San Gabriel Park Plant 6.307 Southside Plant 3.144 Total Capacity 29.251 Wastewater Treatment PlantsMGD San Gabriel Plant 2.500 Pecan Branch Plant 1.500 Dove Springs Plant 2.500 Berry Creek Plant 0.300 Cimarron Hills Plant 0.200 Total Capacity 7.000 2 DR A F T Age One of the greatest issues facing Water Services is the replacement of older water and wastewater system mains. The City of Georgetown has been providing water and wastewater service for over one hundred years. Some of the early infrastructure has exceeded its useful life and requires extensive repair or replacement to continue the delivery of reliable service to the community. The Wastewater improvements being recommended continue the rehabilitation of sanitary sewer mains that may be experiencing inflow and infiltration throughout the City. An aggressive sanitary sewer main improvement program eliminates the potential for Sanitary Sewer Overflows (SSO) and allows for the delivery of reliable wastewater service to the community. Regulatory Changes The City of Georgetown is subject to requirements of the Edwards Aquifer Recharge Zone (EARZ) rules because 98% of the City is over the Edwards Aquifer Recharge Zone. The regulatory requirements of the Texas Commission on Environmental Quality (TCEQ) require testing of at least 20% of the collection system every year, thus testing the entire system every 5 years. The testing is included in the Wastewater CIP program. Once problems are identified, the City has twelve (12) months to make repairs. A significant portion of the capital budget for the Wastewater Utility is dedicated for inspection and repair of existing mains. 3 DR A F T 2014/15 2015/16 2016/17 2017/18 2018/19 Total (Thousands of dollars) Projected Annual Project Cost Water $3,625$6,461$4,952$7,385$9,106$31,529 Wastewater $9,094$13,649$15,367$16,249$45,339$99,698 Debt Issuance Cost $0$0$512$547$2,374$3,433 Sources of Funding Operating Revenue $10,814$18,205$7,500$10,000$2,000$48,519 Bond Proceeds $0$0$11,369$12,167$52,745$76,281 Impact Fees $1,270$1,270$1,308$1,347$1,388$6,583 Interest & Other $635$635$654$667$686$3,277 In2010,theCityupdateditsimpactfees.Thenewmaximumfeesare$4,714forwaterand$1,694forwastewaterand$5,240 forwastewaterintheSouthForkbasin.TheCityCouncilsetthecurrentfeesat$3,511forwaterand$1,694forwastewaterand $2,927 for wastewater in the South Fork basin. City of Georgetown, Texas Water Services Capital Improvement Program 2014/15 to 2018/19 TheCity’sfiveyearCapitalImprovementProgramfundingcomesfromacombinationofcash,debtfunding,andimpactfees. Actualamountofdebtissueswillbedetermineduponeachindividualyear’sconsiderationofactualresourcesavailable, coverage requirement and other considerations. Operating RevenueBond Proceeds Impact Fees Interest & Other Combined 5 Year Estimated Funding Sources 4 DR A F T EST C.I.P. 2014-15Water Improvements April 2014 U0 1.50.75 Miles Document Path: L:\Division\Gus\ENGINEERING SUPPORT\PROJECTS\CIP\2014-15\CIP 2014-15 Water Improvements.mxd 2014-15 Water Improvements 2nd St Shell Rd. Water (h-3) W 11th St Rabbit Hill EST City Limits EST 5 DR A F T Prior Project Year 14/15 15/16 16/17 17/18 18/19 (Thousands of dollars) Current Projects: Water Mains 1,794 1,912 6,245 3,415 5,602 6,814 Pump and Storage Upgrades 5,954 1,713 216 1,537 1,783 2,292 Totals 7,748 3,625 6,461 4,952 7,385 9,106 City of Georgetown, Texas Water Capital Improvement Program 2014/15 to 2018/19 Projected $0 $1,000 $2,000 $3,000 $4,000 $5,000 $6,000 $7,000 $8,000 $9,000 $10,000 09 / 1 0 10 / 1 1 11 / 1 2 12 / 1 3 13 / 1 4 14 / 1 5 15 / 1 6 16 / 1 7 17 / 1 8 18 / 1 9 Th o u s a n d s Water Capital Project Cost 6 DR A F T Responsible Division: Water Services Financial Plan (thousands of dollars) : Prior Budget Year 14/15 15/16 16/17 17/18 18/19 Total 1,794 1,912 6,245 3,415 5,602 6,814 25,782 Description : Funding Sources : Funded by cash from operations 14/15 15/16 16/17 17/18 18/19 Water- Street Rehab 247 146 - - - Shell Rd. Water (H-3)1,665 4,756 - - - N. Side Old TownN.Austin Ave to Stadium Dr - - - - - West Loop (H-1B) Ph IInnerspace to Thousand Oaks- 408 1,000 - - Lakeway To SH 195 C-2d - 935 2,415 - - Rabbit Hill Water (RH-1)- - - 2,801 Shell Rd. Water (H-5)- - - 2,801 - Airport Rd. to Lakeway (C-6)- - - - 996 N.W. IH 35 Water (C-2a)- - - - 1,994 SH 195 Water (H-4)- - - - - Lakeway Water (C-5)- - - - - South IH 35 Water (H-1b)- - - - 3,824 Operating Budget Impact (000):No Material Impact 14/15 15/16 16/17 17/18 18/19 Notes: City of Georgetown, Texas Capital Improvement Program Water Mains Projected Projectentailsreplacementofwaterlinesintheserviceareatoimprovefirefightingcapabilitiesandeliminateaged, undersizedlines.ReplacementoflinesiscoordinatedwiththeStreetDepartmentCIPprogramtoreplacewaterlinespriorto or during street rehabilitation to minimize the impact of maintenance on upgraded streets. Photo / Map Placeholder Subprojects (000): Basis for Estimate 7 DR A F T Responsible Division: Water Services Financial Plan (thousands of dollars) : Prior Budget Year 14/15 15/16 16/17 17/18 18/19 Total - 1,713 216 1,537 1,783 2,292 7,541 Description : Funding Sources : Funded by cash from operations, utility revenue bonds and impact fees. 14/15 15/16 16/17 17/18 18/19 Rabbit Hill Elevated Storage Tank(EST)1,713 - - - - Park Water Treatment Plant Pump Station - 216 1,199 - - West PP Pump Station (2018)- - 338 1,783 - Southeast EST - - - 458 West PP GST (2018)- - - - 1,834 - - - - - Operating Budget Impact (000):No Material Impact 14/15 15/16 16/17 17/18 18/19 Notes: Rabbit Hill Elevated Storage Tank will be constructed to meet current and future system demand. Future projects consist of routine maintenance of the Park Water Treatment Plant clearwell is scheduled for removal and has become a regulatory issue and West PP pump station. City of Georgetown, Texas Capital Improvement Program Pump and Storage Upgrades Projected Photo / Map Placeholder Subprojects (000): Basis for Estimate 8 DR A F T Prior Project Year 14/15 15/16 16/17 17/18 18/19 (Thousands of dollars) Current Projects: Wastewater Interceptors 1,644 5,711 9,758 9,713 7,098 26,081 Pumping Upgrades 250 3,383 368 1,377 5,593 10,199 Plant Upgrades - - 3,523 4,277 3,558 9,059 Totals $1,894 $9,094 $13,649 $15,367 $16,249 $45,339 City of Georgetown, Texas Wastewater Capital Improvement Program 2014/15 to 2018/19 Projected $0 $5,000 $10,000 $15,000 $20,000 $25,000 $30,000 $35,000 $40,000 $45,000 $50,000 09 / 1 0 10 / 1 1 11 / 1 2 12 / 1 3 13 / 1 4 14 / 1 5 15 / 1 6 16 / 1 7 17 / 1 8 18 / 1 9 Th o u s a n d s Wastewater Capital Project Cost 9 DR A F T `_ `_ SUN CITY LIFT STATION Berry Creek Interceptor (BCI-6) Snead Dr. WW Berry Creek Interceptor (BCI-5) EARZ Berry Creek Interceptor (BCI-4) W 11th St Lift Station Decommission New Lift Stationand Force Main SAN GABRIEL WWTP BERRY CREEK WWTP PECAN BRANCH WWTP DOVE SPRINGS WWTP C.I.P. 2014-2015Wastewater Improvements April 2014Document Path: L:\Division\Gus\ENGINEERING SUPPORT\PROJECTS\CIP\2014-15\CIP 2014-15 Wastewater Improvements.mxd U0 10.5 Miles LS Decommission LS New `_ `_ CIP Projects City Limits 2014-15 WastewaterImprovements EARZ LineInspection Area 10 DR A F T Responsible Division: Water Services Financial Plan (thousands of dollars) : Prior Budget Year 14/15 15/16 16/17 17/18 18/19 Total 1,644 5,711 9,758 9,713 7,098 26,081 60,005 Description : Funding Sources : Funded with cash from operations. 14/15 15/16 16/17 17/18 18/19 Wastewater - street projects 136 200 - - - EARZ 2,500 2,000 2,000 1,500 1,000 S. Interceptor (SI-P4)- 154 - - - Snead Dr. WW 1,040 - - - - S. IH 35 Force MainInnerspace to Thousand Oaks- 296 - - - Berry Creek Interceptor (BCI-4)351 1,489 - - - Berry Creek Interceptor (BCI-5)404 1,347 - - - Berry Creek Interceptor (BCI-6)1,280 4,272 - - - Berry Creek Interceptor (BCI-3)- - 7,713 - - Inter. LS Decomm (Int-LS)- - - 5,598 - Other Interceptors 25,081 Operating Budget Impact (000): 14/15 15/16 16/17 17/18 18/19 Possible operational savings due to reduced inflow and infiltration (12) (12) (12) - - Notes: Photo / Map Placeholder Subprojects (000): Basis for Estimate City of Georgetown, Texas Capital Improvement Program Wastewater Interceptors Projected Project entails replacement of wastewater lines in the service area to improve flow and eliminate aged, undersized lines. Replacement of lines is coordinated with the Street Department CIP program to replace wastewater lines prior to or during street rehabilitation to minimize the impact of maintenance on upgraded streets. EARZ rehabilitation and the demand on the budget leave only a small amount of funds to be set aside for projects that have not specifically been identified. 11 DR A F T Responsible Division: Water Services Financial Plan (thousands of dollars) : Prior Budget Year 14/15 15/16 16/17 17/18 18/19 Total - - 3,523 4,277 3,558 9,059 20,417 Description : Funding Sources : Funded with cash from operations and impact fees. 14/15 15/16 16/17 17/18 18/19 Pecan Branch WWTP Expansion - 3,523 3,523 - - Cimarron Hill WWTP Expansion - - 754 1,927 - Northlands WWTP - - - 1,631 9,059 - - - - - Operating Budget Impact (000): 14/15 15/16 16/17 17/18 18/19 Electrical cost 1 1 1 - - Notes: This project is to satisfy the TCEQ rule of 80% capacity. The Pecan Branch Waste Water Treatment Plant(WWTP) will be expanded by 1.5MG to meet the compliance of the current capacity and future growth. Future projects consist of other capacity improvements and/or the new Northlands WWTP. City of Georgetown, Texas Capital Improvement Program Plant Upgrades Projected Photo / Map Placeholder Subprojects (000): Basis for Estimate 12 DR A F T Responsible Division: Water Services Financial Plan (thousands of dollars) : Prior Budget Year 14/15 15/16 16/17 17/18 18/19 Total 250 3,383 368 1,377 5,593 10,199 21,170 Description : Estimated Project Cost (000): Construction 17,990 Design 3,180 Preconstruction - Other - Total $21,170 Funding Sources : Funded with cash from operations. 14/15 15/16 16/17 17/18 18/19 Lift Station Upgrades 250 250 250 250 250 ACM LS decommission 152 - - - - Westinghouse LS (New)2,981 - - - - Westinghouse LS & FM (rebuild)- 118 200 657 - Berry Creek LS & FM (BCI-LS)- - 927 4,686 - Dove Springs WWTP LS - - - - 2,295 McNutt LS & FM - - - - 2,768 Cowan Creek LS & FM - - - - 4,886 Operating Budget Impact (000): 14/15 15/16 16/17 17/18 18/19 Power savings (7) (7) (7) - - Notes: Subprojects (000): Basis for Estimate Project is a multi-year project to upgrade or decommission the City's 33 lift stations (LS). Included are control panel upgrades, SCADA and fiber upgrades, pump upgrades, emergency diesel installation, installation of safety grates, etc. Photo / Map Placeholder City of Georgetown, Texas Capital Improvement Program Pumping Upgrades Projected 13 DR A F T Energy Services Introduction The Energy Services Utility maintains a Capital Improvement Program (CIP) to address the community’s need for superior electric service. The CIP is developed by incorporating several factors including service improvement, increased reliability, equipment aging, and extension of service within the certificated service area, regulatory changes, competition within dually certified areas, and support for economic development. The City operates and maintains an energy delivery system including seven substations and 394 miles of distribution lines consisting of both 12.5kV and 25kV. In addition to energy delivery, the Energy Services Utility operates the SCADA system, fiber-optic communications network, and the AMR system. These additional systems support collectively the electric and water utilities. Growth Over the past ten years, the City of Georgetown Electric distribution system has experienced rapid growth, with the addition of several new residential and commercial developments in the system’s service area. The system anticipates a continued growth of 15% in the service area over the next five years. The Capital Improvement Plan (CIP) includes projects over the next five years to add power bank additions at substations along with other substation support and modifications to address growth and reliability. Additionally, the CIP includes new extensions of overhead and underground feeders to new commercial and residential developments, system improvements projects for load and reliability control, as well as the service extensions from the existing distribution system to service new customers. Substations MVA Chief Brady 80.3 East 46.7 Gabriel 56.0 Georgetown 44.8 Glasscock 33.6 Rivery 80.3 South 46.7 Total Capacity 388.4 Distribution lines Electric Lines 394.0 Fiber lines 77.0 Networked AMR Meters22,636.0 14 DR A F T Age To address the aging of the system, the CIP includes projects to inspect, treat or replace deteriorated poles and rehabilitate aging facilities. In 2008/09, the Utility began a long term project to identify and rehabilitate overhead & underground facilities system wide including phased conversion of portions of its 12.5kV system to 25kV for reliability. Regulatory Changes The City’s electric system is subject to reliability standards of the North American Electric Reliability Council (NERC), operational control and reliability through the Electric Reliability Council of Texas (ERCOT). Due to the deregulated electric market in Texas, and the City’s status as a non-opt-in municipal retail provider, the City must continue to monitor developments in the Texas market place. The replacement of the AMR system with an AMI system will support regulatory changes related to Smart-Grid. The City has a Conservation and Environmental department to focus on conservation within the electric utility, including the provision for capital investment in conservation-related projects. 15 DR A F T 2014/15 2015/16 2016/17 2017/18 2018/19 Total (Thousands of dollars) Projected Annual Project Cost 6,903 7,819 6,795 4,795 4,795 $31,107 Debt issuance cost 74 103 71 - - $248 Sources of Funding Operating Revenue $4,500$4,500$4,500$4,795$4,795$23,090 Utility Revenue Debt $2,477$3,422$2,366$0$0$8,265 Prior Project Year 14/15 15/16 16/17 17/18 18/19 (Thousands of dollars) Current Projects: Substations / Communication 3,402 2,403 3,319 2,295 295 295 System Improvements 3,895 4,500 4,500 4,500 4,500 4,500 Totals 6,903 7,819 6,795 4,795 4,795 City of Georgetown, Texas Electric Capital Improvement Program 2014/15 to 2018/19 Projected $0 $1,000 $2,000 $3,000 $4,000 $5,000 $6,000 $7,000 $8,000 $9,000 09 / 1 0 10 / 1 1 11 / 1 2 12 / 1 3 13 / 1 4 14 / 1 5 15 / 1 6 16 / 1 7 17 / 1 8 18 / 1 9 Th o u s a n d s Electric Capital Project Cost 16 DR A F T XY XY XY XY XY XY XYRIVERY GABRIEL GLASSCOCK GEORGETOWN CHIEF BRADY GEORGETOWN EAST GEORGETOWN SOUTH C.I.P. 2014-2015Energy Services April 2013 L:\Division\gus\GIS-CAD\CIPBudget\CIP13-14\GIS\EnergyServices.mxd U 0 1.50.75 Miles Electric SubstationsXY Electric Dual/Triple Certified Areas Electric Service Boundary Georgetown City Limits System ImprovementsSystem ExpansionFiber Network Expansion and ReplacementsElectric System Engineering Energy Services Projects in multiple locations (system wide) 17 DR A F T Responsible Division: Energy Services Financial Plan (thousands of dollars) : Prior Budget Year 14/15 15/16 16/17 17/18 18/19 Total 3,402 2,403 3,319 2,295 295 295 12,009 Description : Funding Sources : Funded by cash from Electric Utility. 14/15 15/16 16/17 17/18 18/19 Substations 1,753 3,024 2,000 - - Communication 650 295 295 295 295 Operating Budget Impact (000): 14/15 15/16 16/17 17/18 18/19 Transformation Cost Savings (89) (326) (359) - - Notes: Photo / Map Placeholder Basis for Estimate City of Georgetown, Texas Capital Improvement Program Substations / Communication Projects (000): Projected The cost associated with these projects are for installation of new or replacing existing power banks. This project also provides for engineering, construction and installation of devices related to operating and maintaining City's electric Substation including SCADA upgrades. 18 DR A F T Responsible Division: Energy Services Financial Plan (thousands of dollars) : Prior Budget Year 14/15 15/16 16/17 17/18 18/19 Total 3,895 4,500 4,500 4,500 4,500 4,500 26,395 Description : Funding Sources : Funded by cash from the Electric Utility. 14/15 15/16 16/17 17/18 18/19 System Improvements 3,460 3,505 3,505 3,505 3,505 Operational 1,040 995 995 995 995 Operating Budget Impact (000):No Material Impact 14/15 15/16 16/17 17/18 18/19 Notes: Photo / Map Placeholder Basis for Estimate City of Georgetown, Texas Capital Improvement Program System Improvements Projects (000): Projected These projects provide for various system improvements and modifications to the existing electric system overhead and underground main and branch feeder circuits. Projects include the replacement and modification of facilities, circuit ties for reliability improvements, voltage conversions, conductor replacement or upgrades, capacitor and sectionialization switches for system performance. 19 DR A F T